The Channel Tunnel - The World's Largest Undersea Tunnel
Introduction:- Now
and then, with the advancement of technology, civil engineers have been creating marvels. One such commendable engineering wonder is the Channel
Tunnel. The Channel Tunnel also referred to as the Eurotunnel or Chunnel, is
a 50.45 km-long undersea rail tunnel below the Strait of Dover in the English
Channel. It is one of the longest underwater rail tunnels in the world,
connecting the Folkestone in Kent, the UK with Coquelles in Pas-de-Calais,
France. This tunnel has cut travel times between the UK and mainland Europe dramatically. The tunnel's average depth is 50 meters below the seabed, and the lowest point 75 meters below. Started in 1887 and completed in 1994, the
Eurotunnel is one of the most challenging civil engineering projects of the
20th century. It is regarded as one of the "Seven Wonders of the Modern
World" by the American Society of Civil Engineers. |
|
Construction:-
The construction of this tunnel was
first proposed in 1802. However, due to the lack of appropriate techniques and engineering
skills, it was aborted. The project was officially launched in 1973. The
engineering, construction, procurement, and project management services contract
was awarded to Bechtel. The Eurotunnel consists of three tunnels running
parallel to each other, including two rail tunnels and one service tunnel. The
rail tunnels, which are located 30 meters apart, have a diameter of about 7.6
meters while the service tunnel which is situated in between the two rail
tunnels has a diameter of about 4.8meters. A total of 11 tunnel boring
machines (TBMs), each weighing approximately 450 tonnes, were used to dig the
tunnels, at the rate of 250 feet a day. Five TBMs dug from France; six TBMs dug
from the UK. Machines with a combination of extremely high-pressure water jets
and rotating disc cutters were used to burrow through the land beneath the
Channel.
Geology:-
Assessments
of the geotechnical conditions along the route of the tunnel had started in
1956. Surveyors began collecting data about the marine environment and geology
to determine the most suitable rock strata and prevent any geological hazard
along the way of the tunnel. The survey revealed that the top and middle layers
had a high level of porosity, which made it unsuitable for digging. The upper
layers had sand and gravel, which were hard to drill.
Surveying:-
Surveying was an essential part of channel
tunneling construction, without proper and accurate surveying the project
would have ended as a disaster. Marine soundings and samplings were carried out
by Thomé de Gamond during 1833–67, which established the seabed depth at a
maximum of 55 meters (180 ft.) and the continuity of geological strata
(layers). Surveying continued over many years, with 166 marine and 70 land-deep
boreholes being drilled and over 4,000-line-kilometres of the marine
geophysical survey completed. Surveys were undertaken in 1958–1959, 1964–1965,
1972–1974 and 1986–1988.
Impacts on Environment:-
Much of the land used had traditionally been used for agricultural
means. A large volume of vegetation was destroyed on land that was temporarily
and permanently acquired for the construction and subsequent operation of the
Channel Tunnel.
Soil disposal: Early on in the design process developers
acknowledged that soil disposal was an issue that had to be managed. It was
known that the Channel Tunnel would have a mammoth impact on the landscape due
to earthworks. The sand was pumped rather than trucked to reduce the
environmental impact of this activity. It was observed that soil disposal had a
significant effect on land and vegetation.
Water pollution: Although precautionary measures were taken, silt deposits did accumulate, and streambed cleaning had to be undertaken by Eurotunnel to cleanse the waterways to evade damaging stream flora and fauna.
- Ayusha Barik & Shailesh Patro
Comments
Post a Comment